time Line

1 April 2000

Land Acquired

On the 1st April 2000, the land of Masjidur-Raoof was acquired.

1 April 2000

7 July 2000

Transfer Registered

On the 7th July 2000, the transfer of the land was registered.

7 July 2000

30 August 2001

Buliding Plands Approved

On the 30th August 2001, the building plans of the Masjid was approved.

30 August 2001

17 Junuary 2002

Completion of Foundation and trenches

On the 17th January 2002, the Foundation and Trenches were completed.

17 Junuary 2002

25 May 2002

Brickwork started

On the 25th May 2001, brickwork started on the Masjid.

25 May 2002

21 September 2002

Roof Erected

On the 21st September 2002, the roof of the Masjid was erected

21 September 2002

5 November 2002

First Taraaweeg

On the 5th November 2002, the first Taraaweeg Salaah was perform in the Masjid.

5 November 2002

11 October 2003

Official Opening

On the 11th October 2003, Construction of the Masjid was completed and the official opening of the Masjid took place.

11 October 2003

17 October 2002

First Jumu’ah Salaah

On the 7th October 2003, the First Jumu’ah Solaah was performed.

17 October 2002

1 December 2010

Opening of Lecture Room

On the 1st of December 2003, The opening of a lecture Room, installed with computers and data projector, took place.

1 December 2010