1 April 2000
Land Acquired
On the 1st April 2000, the land of Masjidur-Raoof was acquired.
7 July 2000
Transfer Registered
On the 7th July 2000, the transfer of the land was registered.
30 August 2001
Buliding Plands Approved
On the 30th August 2001, the building plans of the Masjid was approved.
17 Junuary 2002
Completion of Foundation and trenches
On the 17th January 2002, the Foundation and Trenches were completed.
25 May 2002
Brickwork started
On the 25th May 2001, brickwork started on the Masjid.
21 September 2002
Roof Erected
On the 21st September 2002, the roof of the Masjid was erected
5 November 2002
First Taraaweeg
On the 5th November 2002, the first Taraaweeg Salaah was perform in the Masjid.
11 October 2003
Official Opening
On the 11th October 2003, Construction of the Masjid was completed and the official opening of the Masjid took place.
17 October 2002
First Jumu’ah Salaah
On the 7th October 2003, the First Jumu’ah Solaah was performed.
1 December 2010
Opening of Lecture Room
On the 1st of December 2003, The opening of a lecture Room, installed with computers and data projector, took place.